Heritage Park, the open-air stage park at Main Street and Burnett Avenue, is set to reopen with a ribbon cutting Thursday, Oct. 15, as the city formally dedicates the second phase of its downtown rebuild.
City board records list the event as the "Phase 2 and Heritage Park Dedication" at the park, 324 W. Main St. Minutes of the Main Street Advisory Board's Aug. 27 meeting say the mayor picked a Thursday evening so the ceremony would coincide with downtown's weekly Twilight Shopping, and that staff was planning a concert as part of the celebration.
A tourism report to the Convention and Visitors Bureau Advisory Board in September described the dedication as including live music and a chance to show off the park's new stage.
The city has not posted a start time. The Aug. 27 minutes say a private dedication for firefighters and the families of those who lost their lives in the 1989 fire will be held before the public ceremony.
A memorial returns
The park sits on the site of the December 1989 blaze that destroyed a two-story department store on Main Street. A Denison firefighter died fighting that fire, and a memorial to him had stood in the park, KXII reported in February 2025.
Main Street Director Donna Dow told the station then that the memorials would be kept, placed around a tree in the park and expanded with more information about the people they honor.
Two years of construction
Phase 2 of the Designing Downtown Denison project began May 6, 2024, according to the city's project page. It covers the 300 and 400 blocks of Main Street, the Fannin and Main intersection, Heritage Park and the alleys on both sides of Main. The city's schedule had the park itself under construction from January 2025 into June 2026, and the work ran past that.
When the Rhythm & Rails music festival was held in September, its main stage was moved to a Depot District lot at 111 W. Main because of Heritage Park construction delays, the Main Street board's minutes say.
By late August, the remaining Phase 2 work was mainly cleanup and work inside the park, city staff told the board.