Emergency water link with Sherman goes to council Monday, along with $1.17 million in sewer and wall repairs already done

A $311,534 engineering contract would design two normally closed connections so either city could draw water from the other in a crisis. Council will also ratify five unbudgeted repairs and vote on up to $20 million in utility debt.

Tobias Iverson

October 13, 20263 min read

Denison and Sherman would be able to lean on each other's water systems in an emergency under a design contract the City Council takes up Monday.

The item, on the consent agenda for the Oct. 19 meeting, would hire Plummer Associates for up to $311,534 to investigate, engineer and design two connections between the cities' systems and to support Denison through construction.

According to the staff memo, the connections would stay closed and be maintained regularly, and would be opened only in an emergency, such as when a city's supply or a key part of its system is compromised.

The project grew out of a joint Denison and Sherman "Partners in Progress" meeting earlier this year, the memo says.

A feasibility study by Plummer, dated October 2025 and included in the packet, found a link workable but said the details matter: some options for sending Denison water south could require added pumping or limits on demand, while Sherman's Northwest pressure zone was judged the best source for supplying Denison.

The engineers also recommended testing for corrosion risk at the chosen sites because mixing water from the two systems could raise corrosion concerns.

The work is budgeted in Denison's 2027 utility capital plan. The memo says a later interlocal agreement will spell out how the two cities split the cost.

Paying for repairs that could not wait

In a separate vote, the council is asked to ratify $1,170,989.99 in emergency work from the fiscal year that ended Sept. 30, all of it finished or nearly finished. Staff said each job was beyond what the budget's small contingency could absorb:

  • Day Street railroad crossing, $454,800: a collapsed 18-inch sewer line under active tracks was causing a sinkhole beneath them. Crews bored about 300 feet of 36-inch pipe while trains kept running.
  • FM 84 and Highway 69, $322,748.55: creek erosion after heavy rains exposed a leaking 21-inch sewer main in a washout more than 15 feet deep.
  • Duck Creek and FM 84, $221,501.44: an 18-inch sewer main collapsed in several places about 16 feet underground, causing an overflow.
  • Heritage Park, $97,800: a structural engineer flagged the old brick wall on the park's east side before the rebuilt park reopened; a historic masonry firm repaired it with salvaged brick.
  • North Texas Regional Airport, $74,140: broken and missing water valves replaced at three intersections near a new hangar, all at once to limit water shutoffs for Denison Industries.

Up to $20 million in utility debt

The council will also vote on certificates of obligation of up to $20 million for water and sewer projects in the city's 10-year capital plan, to be repaid from utility revenue. The draft ordinance lists $19,695,000 and states that no petition protesting the debt was received after the council approved the notice of intent on Aug. 17.

Staff wrote that the city issues these certificates every year to fund phases of its utility projects.

The meeting begins at 6 p.m. at City Hall, 300 W. Main St.

Sources

denisontx.api.civicclerk.com

denisontx.api.civicclerk.com

Share

Tobias Iverson

Tobias Iverson covers Denison city hall, the council, and county government.